Ark7 Qualifies a $23.2 Million Data Center Offering in Which the Developer Can Earn 74% Partly Through Project Debt

Investors in Ark7's new series would share in at most 26% of a planned 10 MW data center in Soperton, Georgia, alongside up to 41,900 interests Ark7 can receive without paying cash. The developer earns up to 74% by arranging $57.72 million of funding, which can include loans the project must repay.

By , Head of Research· AltStreet Research
Headline card for Ark7 Qualifies a $23.2 Million Data Center Offering in Which the Developer Can Earn 74% Partly Through Project Debt

Key facts

14
  1. Ark7 AIDC I, LLC, a Delaware series LLC formed in 2026 with Ark7 as managing member, filed an offering statement on Form 1-A on November 9, 2026 and an amendment on November 18 (accession 0002159048-26-000004); the SEC qualified it on November 23, 2026.
  2. Series #VNATI offers up to 168,000 interests at $138.00 each, $23,184,000 in total, with no minimum and rolling closings; no escrow agent is engaged.
  3. The series' asset is a Class A membership interest in Soperton Data Center I, LLC, which plans a data center with about 10.0 MW of utility capacity and 7.6 MW of tenant IT load on about 7.5 acres at 926 Commerce Dr, Soperton, Georgia.
  4. First Amendment to Investment Agreement, dated as of November 2, 2026 (exhibit 6-2 to the Form 1-A, accession 0002159048-26-000002): the Base Project Cost is fixed at $78,000,000 'solely for purposes of determining contractual Economic Percentage Interests' and is not adjusted because actual project cost is higher or lower.
  5. Same agreement: the series earns a 26% Economic Percentage Interest for $20,280,000 of cash actually contributed; VCI Energy Inc., the sponsor member, earns 74% upon full recognized delivery of the remaining $57,720,000, which it may arrange through its own funds, qualifying project company construction and bank loans, equipment or vendor financing, customer deposits or prepayments, or other permitted sources.
  6. Same agreement: 'Project Company debt and refundable customer deposits remain liabilities, not paid-in Sponsor equity, notwithstanding their contractual recognition for vesting,' and vested sponsor interests are not reversed because recognized borrowings are repaid or refinanced.
  7. Same agreement: a negotiated $10,000,000 project-origination and land-and-power value is attributed to the sponsor as part of the consideration for its 74%; it does not reduce the $57,720,000 funding responsibility. Actual land and power-upgrade spending of about $3,500,000 is included in the $78,000,000 base.
  8. The series would hold 66 2/3% of the project company's Class A voting power and the sponsor 33 1/3%; Ark7 is the series' managing member and asset manager, and the project company manager is Ark7 or an Ark7 entity.
  9. Circular: 5,600 series interests were outstanding before the offering and 173,600 after it; in addition, up to 41,900 Sponsor Interests may be issued to Ark7 Inc. without cash consideration under Section 3.4(c) of the operating agreement, vesting as the series acquires its project interest.
  10. AltStreet's arithmetic: if all 41,900 Sponsor Interests vest alongside 173,600 investor interests, investors would hold about 80.6% of the series, or about 21% of the project's economics at full funding.
  11. Ark7 receives a sourcing fee of $1,428,168 and an asset management fee of 15% of the series' free cash flow available for distribution.
  12. Notes to the financial statements: between October 13 and November 2, 2026 the series sold 56 interests in a Rule 506(c) private placement at $11,050 each, $618,800 in total; after a 100-for-1 split these are 5,600 interests at $110.50, against the $138.00 Reg A price. The proceeds are held by Ark7 Inc. on the series' behalf.
  13. A Form D filed October 14, 2026 (accession 0002159048-26-000001) reported a $27,600,000 offering with no sales at that date.
  14. The project company signed a land purchase agreement with the Treutlen County Development Authority on September 23, 2026 and expects to close by December 22, 2026; the circular names no tenant or offtaker.

Ark7, a platform that sells fractional shares of rental homes, has qualified a Regulation A offering for a stake in a data center. Series #VNATI of Ark7 AIDC I, LLC is offering up to $23,184,000 of interests at $138.00 each to fund part of a planned 10 MW data center in Soperton, Georgia. The SEC qualified the offering on November 23, 2026.

The series can earn up to 26% of the project's economics. The developer, VCI Energy Inc., can earn up to 74% by arranging $57.72 million of funding, and that funding can include construction loans, vendor financing and customer deposits that the project company must repay. Investors also share the series with Ark7, which can receive up to 41,900 interests without paying cash.

How the 74% is earned

An amendment to the investment agreement, dated as of November 2, 2026 and filed as an exhibit to the offering statement, sizes each side's economics against a fixed $78 million base. The agreement says that figure is used only to set economic percentages and is not adjusted if the actual project costs more or less. Cost overruns do not dilute the series' right to reach 26%, and savings do not increase it.

The sponsor's funding counts when it is actually disbursed to the project, whether it comes from VCI Energy's own money or from loans and deposits it arranges. The agreement states that "Project Company debt and refundable customer deposits remain liabilities, not paid-in Sponsor equity, notwithstanding their contractual recognition for vesting," and that vested sponsor interests are not reversed when those borrowings are repaid or refinanced. So the developer can earn ownership partly by arranging financing that the project, including the series' share of it, must service.

The agreement also attributes to the sponsor a negotiated $10 million project-origination and land-and-power value as part of the consideration for its 74%. That value is not cash and does not reduce the $57.72 million the sponsor must arrange. Actual land and power-upgrade spending of about $3.5 million is part of the $78 million base.

ProvisionWhat the agreement says
Base project cost for sizing economic interests$78,000,000, fixed; not adjusted for actual cost
Series cash for its full 26%$20,280,000 actually received by the project company
Sponsor funding for its full 74%$57,720,000 of recognized funding
What counts toward the sponsor's shareIts own funds, qualifying construction and bank loans, equipment or vendor financing, customer deposits or prepayments, other permitted sources
Negotiated land-and-power value$10,000,000, part of the consideration for the 74%; not cash and not a reduction of the $57,720,000

Source: First Amendment to Investment Agreement dated as of November 2, 2026, exhibit 6-2 to Ark7 AIDC I's Form 1-A filed November 9, 2026.

What investors would own

Investors buy interests in the series, not in the project. The series contributes its cash to Soperton Data Center I, LLC as equity, and its share of the project's economics is 26% multiplied by the cash it actually delivers divided by $20,280,000. If the offering raises less, the share is smaller.

Within the series, investors are not the only holders. The circular says 5,600 interests were outstanding before the offering and 173,600 would be after it, and that up to 41,900 more, called Sponsor Interests, may be issued to Ark7 Inc. without cash, vesting as the series acquires its project interest. If all of them vest, investors would hold about 80.6% of the series, or about 21% of the project's economics at full funding, by AltStreet's arithmetic.

Ark7 is also paid a sourcing fee of $1,428,168 from the offering proceeds and an asset management fee equal to 15% of the series' free cash flow available for distribution. The 5,600 earlier interests were sold in a private placement between October 13 and November 2 at the equivalent of $110.50 each after a 100-for-1 split, for $618,800; the Regulation A price is $138.00. A Form D filed October 14 had reported no sales at that date.

Control

The series, which Ark7 manages, would hold two-thirds of the project company's Class A voting power and appoint its manager, which is Ark7 or an Ark7 entity. VCI Energy holds the other third, with rights the circular describes as protective, and is responsible for development, land and power, construction, permitting, utility coordination, financing and offtaker arrangements.

Where the project stands

The project company signed a purchase agreement for about 7.5 acres from the Treutlen County Development Authority on September 23, 2026 and expects to close by December 22, 2026. The circular names no tenant or offtaker and lists a utility service agreement among the steps still ahead. In the planned model the project company owns the land, building, power and cooling, and a tenant owns the computers and pays rent based on reserved IT capacity.

The $78 million base is a contractual figure for dividing economics, not a construction budget, and the filings do not give the project's expected actual cost, its construction financing or a tenant.

See the opportunity. Understand the risk.

Get the latest on Ark7

Follow the latest on Ark7, discover new deals, and keep an eye on the risks. Get market news, platform updates, and independent research that helps you see beyond the pitch, delivered to your inbox.

New dealsMarket newsPlatform updates

Make your next move an informed one

Get the latest on Ark7 and the wider alternative markets. Join free.

Independent intelligence from AltStreet. No hype. No sponsor spin.

Sources

  1. Ark7 AIDC I, LLC, offering circular, Form 1-A/A filed November 18, 2026 (accession 0002159048-26-000004) — SEC EDGAR
  2. First Amendment to Investment Agreement, dated as of November 2, 2026 (exhibit 6-2 to Form 1-A filed November 9, 2026) — SEC EDGAR
  3. Soperton Data Center I, LLC operating agreement (exhibit 6-3 to Form 1-A filed November 9, 2026) — SEC EDGAR
  4. Notice of qualification, Ark7 AIDC I, LLC, November 23, 2026 — SEC EDGAR
  5. Ark7 AIDC I, LLC, Form D filed October 14, 2026 (accession 0002159048-26-000001) — SEC EDGAR
  6. Ark7 review — AltStreet